Temporary Works and Slope Stability
Client: Knights Brown
Project Location: Rover Way / Lamby Way, Cardiff
Outcome
ESP provided geotechnical consultancy services to Knights Brown whilst they were in the construction phase of the Cardiff Coastal Defence Scheme.
Part of the Cardiff Coastal Defence Scheme included the construction of a sheet piled wall in close proximity to the Rhymney River and highway infrastructure. Slope Stability modelling was undertaken to assess the existing condition and the likely temporary condition during construction, which included high loads from piling rigs and associated plant.
The ground conditions in the area are notorious for poor strength characteristics; this combined with a slope and high construction loads presented a series of technical challenges. Rather than simply identifying problems, ESP provided practical engineering advice to the Knights Brown team to manage risks and progress the scheme safely within the site constraints.
Introduction
Recent modelling has shown that Cardiff Bay is at risk of flooding; Cardiff Council and the Welsh Government help fund an £85 million package for flood and coastal erosion management for 2026 and into 2027.
When completed, the new coastal defences will aim to protect over 1700 homes and 100 businesses, as well as Rover Way, a main arterial route into the city of Cardiff. Protecting this vital industrial road from erosion will also safeguard steelworks, a traveller’s site, Lamby Way recycling centre, a solar farm and other key infrastructure such as substations and pumping stations.

Details
The coastal protection generally involved increasing the height of an existing flood bund, and the addition of rock armor in places to provide added protection. In certain areas, there was insufficient space between infrastructure and the Rhymney River for the higher flood bund to be constructed, alternative methods of protection were designed; this included the incorporation of sheet piles.
ESP were asked to undertake a Slope Stability (link to previous ESP project/video) assessment to help with Temporary Works of the area where the sheet piles would be installed. With the assistance of Knights Brown, several pertinent lines of section were surveyed, which included bathometric surveys of the river channel.
ESP reviewed available design information and carried out a comprehensive independent review of available geotechnical information including:
- Historical ground investigation data.
- Geotechnical Design Reports.
- Topographical information.
- Temporary works proposals.
- Existing and proposed loading conditions considering construction methods and timing.
Analysis of the sections using slope stability software, GeoStudio Slope W and representative material design parameters showed the slope to be marginally stable, as would be expected on an erosional, fluvial slope. Stability factors increased with distance from the edge of the river bank, but significantly low factors of safety were modelled within the working area.
The below images show some of the SlopeW outputs for this phase of modelling.
This initial modelling helped us understand the general stability of the riverbank and its likely performance under load. This enabled us to focus on likely solutions for Knights Brown for their construction methods. The early phases of assessment also suggested that the principal challenge was not simply the temporary works themselves, but the fact that portions of the existing riverbank were already susceptible to instability before construction commenced; and this had to be considered in the programmed works.
Several live modelling sessions were held with Knights Brown to discuss possible construction scenarios and methods and to rule out and unsuitable methods, but to ultimately help chose a safe plan of construction.
The stability varied considerably depending on construction methodology. At one chainage for example, the modelling generally indicated acceptable performance for the proposed piling mat, haul road and piling operations. This provided confidence that the temporary works could function safely in less sensitive areas.
Where more challenging conditions existed, particularly around Chainage 206, ESP identified the specific factors driving instability and highlighted opportunities to improve safety through revised working methods. The assessment demonstrated that piling rig orientation had an effect on stability.
The modelling showed that stability of the bank would likely be impacted and unsafe working conditions were anticipated. The method of work was therefore adjusted and we were able to demonstrate that if the piles were at a suitable depth, the rig and associated plant could safely work behind the recently installed piles.
Due to this, the commencement area of the piling rig had to be extended away from the river edge with the use of sacrificial piles to enable the rig to commence from a safer area.
The River Rhymney meanders in the study area and there were numerous other fluvial features that warranted consideration, such as jetties or former erosional features. This provided another layer of complexity as not only was one line of section sufficient to check the stability of the proposed stability, several lines of section for a single position were needed.
In order to fully assess the stability, the assessment considered drained and undrained conditions and modelling also checked different groundwater and River Rhymney River levels to check the different stability conditions.
ESP worked proactively with Knights Brown to alter the assessment based on emerging conditions, including the alteration of the piling rig equipment, site conditions and groundwater conditions.
The below image shows some of the final models indicating adequate stability factors for the area of work.
In addition to the above slope stability assessment, ESP also identified potential bearing capacity and settlement concerns associated with placement of the temporary flood bund on soft near-surface soils. Preliminary calculations suggested settlements in excess of 90-100 mm were likely, with total settlements potentially exceeding 130 mm in some areas.