Cardiff Coastal Defences

Temporary Works and Slope Stability

Client: Knights Brown
Project Location: Rover Way / Lamby Way, Cardiff
Outcome

ESP provided geotechnical consultancy services to Knights Brown whilst they were in the construction phase of the Cardiff Coastal Defence Scheme. 

Part of the Cardiff Coastal Defence Scheme included the construction of a sheet piled wall in close proximity to the Rhymney River and highway infrastructure.  Slope Stability modelling was undertaken to assess the existing condition and the likely temporary condition during construction, which included high loads from piling rigs and associated plant.  

The ground conditions in the area are notorious for poor strength characteristics; this combined with a slope and high construction loads presented a series of technical challenges.  Rather than simply identifying problems, ESP provided practical engineering advice to the Knights Brown team to manage risks and progress the scheme safely within the site constraints.

Introduction 

Recent modelling has shown that Cardiff Bay is at risk of flooding; Cardiff Council and the Welsh Government help fund an £85 million package for flood and coastal erosion management for 2026 and into 2027.

When completed, the new coastal defences will aim to protect over 1700 homes and 100 businesses, as well as Rover Way, a main arterial route into the city of Cardiff. Protecting this vital industrial road from erosion will also safeguard steelworks, a traveller’s site, Lamby Way recycling centre, a solar farm and other key infrastructure such as substations and pumping stations.

Details

The coastal protection generally involved increasing the height of an existing flood bund, and the addition of rock armor in places to provide added protection. In certain areas, there was insufficient space between infrastructure and the Rhymney River for the higher flood bund to be constructed, alternative methods of protection were designed; this included the incorporation of sheet piles.

ESP were asked to undertake a Slope Stability (link to previous ESP project/video) assessment to help with Temporary Works of the area where the sheet piles would be installed.  With the assistance of Knights Brown, several pertinent lines of section were surveyed, which included bathometric surveys of the river channel. 

ESP  reviewed available design information and carried out a comprehensive independent review of available geotechnical information including:

  • Historical ground investigation data.
  • Geotechnical Design Reports.
  • Topographical information.
  • Temporary works proposals.
  • Existing and proposed loading conditions considering construction methods and timing.

 

Analysis of the sections using slope stability software, GeoStudio Slope W and representative material design parameters showed the slope to be marginally stable, as would be expected on an erosional, fluvial slope.  Stability factors increased with distance from the edge of the river bank, but significantly low factors of safety were modelled within the working area.      

The below images show some of the SlopeW outputs for this phase of modelling. 

This initial modelling helped us understand the general stability of the riverbank and its likely performance under load.  This enabled us to focus on likely solutions for Knights Brown for their construction methods.  The early phases of assessment also suggested that the principal challenge was not simply the temporary works themselves, but the fact that portions of the existing riverbank were already susceptible to instability before construction commenced; and this had to be considered in the programmed works.  

Several live modelling sessions were held with Knights Brown to discuss possible construction scenarios and methods and to rule out and unsuitable methods, but to ultimately help chose a safe plan of construction.

The stability varied considerably depending on construction methodology. At one chainage for example, the modelling generally indicated acceptable performance for the proposed piling mat, haul road and piling operations. This provided confidence that the temporary works could function safely in less sensitive areas.

Where more challenging conditions existed, particularly around Chainage 206, ESP identified the specific factors driving instability and highlighted opportunities to improve safety through revised working methods. The assessment demonstrated that piling rig orientation had an effect on stability.

The modelling showed that stability of the bank would likely be impacted and unsafe working conditions were anticipated.  The method of work was therefore adjusted and we were able to demonstrate that if the piles were at a suitable depth, the rig and associated plant could safely work behind the recently installed piles.

Due to this, the commencement area of the piling rig had to be extended away from the river edge with the use of sacrificial piles to enable the rig to commence from a safer area.    

The River Rhymney meanders in the study area and there were numerous other fluvial features that warranted consideration, such as jetties or former erosional features.  This provided another layer of complexity as not only was one line of section sufficient to check the stability of the proposed stability, several lines of section for a single position were needed. 

In order to fully assess the stability, the assessment considered drained and undrained conditions and modelling also checked different groundwater and River Rhymney River levels to check the different stability conditions.

ESP worked proactively with Knights Brown to alter the assessment based on emerging conditions, including the alteration of the piling rig equipment, site conditions and groundwater conditions. 

The below image shows some of the final models indicating adequate stability factors for the area of work. 

In addition to the above slope stability assessment, ESP also identified potential bearing capacity and settlement concerns associated with placement of the temporary flood bund on soft near-surface soils. Preliminary calculations suggested settlements in excess of 90-100 mm were likely, with total settlements potentially exceeding 130 mm in some areas.

Speak to Us Today

Get in touch with our team via our email, enquiries@earthsciencepartnership.com or phone number, 02920 813385  and we’ll be very happy to help with and discuss any geotechnical engineering project requirements you may have.

For a full list of all ESP capabilities, please click here.

Project Type

Related Projects

Archives

Share this post

This entry was posted in Projects.

We operate within a framework of professional memberships and industry-recognised accreditations, including ISO9001 and ISO 14001, ensuring that our technical delivery is consistently aligned with the highest standards of quality and governance.

Our Accreditations

Client Testimonials

Posted on Google Google
Simon Lewis profile picture
Simon Lewis
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Earth Science Partnership recently completed an independent geo-environmental review for us and I have been extremely impressed with both the quality of their work and the professionalism of the team. The report was comprehensive, balanced and technically robust, helping us navigate a complex evidence base and identify the key issues requiring further consideration. Just as importantly, ESP were approachable and willing to engage constructively with questions arising from the draft report. Special thanks to Daniel Thomas for his time, patience and willingness to explain technical matters in a way that non-specialists could understand. It was clear throughout that the focus was on objective, evidence-led analysis rather than simply telling a client what they wanted to hear. A highly professional consultancy and one I would most happily recommend. Simon Lewis : Secretary : Nant-Y-Calch Conservation Group
Posted on Google Google
Barbara profile picture
Barbara
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Earth Science Partnership has helped us immensely through a , long, stressful and complex situation following a major leak under our property. We had the absolute pleasure of working with Giles Sommerwill, who was with us every step of the way. He helped us to understand the geological conditions and ramifications following such a major leak, and then informed and advised us during the process of agreeing a remedial solution with the water company, as well as helping us address other issues that arose over time. Giles is experienced, knowledgeable and highly qualified. We could not have hoped to work with anyone more professional, reliable or kind. We also felt that Giles was genuinely concerned, not just about our property, but about our well-being. Thanks to him, we highly recommend, and praise, Earth Science Partnership.
Posted on Google Google
Roberta Morgan profile picture
Roberta Morgan
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Having used the services of Earth Science Partnership on two previous occasions, we had no reservations about employing them for a third time. They are very professional and produce excellent detailed reports on what they are able to do. They are prepared to listen to everything you require and would highly recommend them.
Posted on Google Google
Joshua Pike profile picture
Joshua Pike
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
ESP undertook some thorough CMRA (Coal Mining Risk Assessment) works for our site. They showed a surprising level of knowledge into the historical mining methods and establishment of mining sites. Prompt and in-depth reporting and great communication, would definitely recommend.
Posted on Google Google
Duncan Phillips profile picture
Duncan Phillips
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Great client to deal with!
Posted on Google Google
Keri Beal profile picture
Keri Beal
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Great communication, excellent prompt service.
Posted on Google Google
Oliver Stacey profile picture
Oliver Stacey
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
ESP have done some excellent GI works for me and produced some excellent in depth reports for our client (Network Rail)

Speak To Our Experts Today

Earth Science Partnership is a leading geoenvironmental and geotechnical expert, delivering a comprehensive range of specialist services across Wales, England, Scotland, Northern Ireland and Ireland. We have decades of combined experience in our team of industry-recognised experts.

Our work, for homeowners, land owners, developers, and investors is completed in compliance with the latest, relevant industry best practices and guidance. We understand that every project is unique, so we deliver our services tailored to your needs.

Whether you require initial site investigation, complex hazard engineering, or comprehensive environmental impact assessments, the ESP team can support you with a straightforward, cost-effective solution for any stage of your asset development.